Experience • Engineering
Garland Wastewater Treatment Plant
-
Client Garland City
-
Location Garland, Utah
-
Services Construction Administration, Construction Observation, Funding Management, Value Engineering, Project Closeout Support
Project Highlights
-
Supported Garland City during construction of its own wastewater treatment facility, providing construction administration, observation, and funding management services
-
The facility uses AeroMod’s Sequox® treatment process—the first application of the process in Utah—combining continuous clarification with sequencing aeration to achieve stringent nutrient requirements.
-
The compact 7,300-square-foot facility is designed to biologically treat an average daily flow of 0.45 MGD and a peak daily flow of 1.27 MGD.
-
Provided daily observation logs with progress updates, timestamps, and photographs to keep City representatives informed throughout the 18-month construction period.
-
Helped the City navigate COVID-era supply-chain disruptions and significant construction cost increases through ongoing coordination and value engineering.
-
Managed project and funding requirements to help keep construction and professional service costs under the USDA Rural Development-approved budget, despite pandemic-related cost pressures.